October
26, 2018 UPDATE –
Contractor Garney Construction completed installation of the
36-inch water main on the section of Patton Street between E. Jackson Avenue
and Willow Avenue. This section of Patton Street will remain closed through
November 9 for paving and restoration work. Once paving and restoration are
complete on Patton Street, crews will move to Willow Avenue to continue
installation of the 36-inch water main. The Patton Street intersection and
approximately 300 feet of Willow Avenue east of the intersection will be closed
starting October 30 through early November. A second Garney Construction crew
completed installation and testing of a new 8-inch water main along the section
of W. Depot Avenue between N. Gay Street and Williams Street. Tie-ins are
scheduled in the area through October 31, followed by paving and restoration
through November 9.
This
section of W. Depot Avenue will remain closed as part of an ongoing non-KUB
development project in the area.