Depot Avenue Water Main Project


October 26, 2018 UPDATE

Contractor Garney Construction completed installation of the 36-inch water main on the section of Patton Street between E. Jackson Avenue and Willow Avenue. This section of Patton Street will remain closed through November 9 for paving and restoration work. Once paving and restoration are complete on Patton Street, crews will move to Willow Avenue to continue installation of the 36-inch water main. The Patton Street intersection and approximately 300 feet of Willow Avenue east of the intersection will be closed starting October 30 through early November. A second Garney Construction crew completed installation and testing of a new 8-inch water main along the section of W. Depot Avenue between N. Gay Street and Williams Street. Tie-ins are scheduled in the area through October 31, followed by paving and restoration through November 9.
This section of W. Depot Avenue will remain closed as part of an ongoing non-KUB development project in the area.