Friday, October 26, 2018

South Knox Natural Gas Project


October 26, 2018 UPDATE

Pipeline: Restoration work remains in one area between W. Marine Road and Henry Haynes. All other restoration work has been completed.

Gate Station: KUB contractor Cenergy continued conduit installation and pipe testing this week. Next week, crews will be coating and backfilling newly-installed pipe. Conduit and wiring installation will also continue next week.