South Knox Natural Gas Project

October 5, 2018 UPDATE – Pipeline: Restoration work will continue in the area between W. Marine Road and Henry Haynes Road next week. Gate Station: KUB contractor Cenergy continued wiring and piping installation this week. The newly-installed piping will be ready for testing next week.

Overall Project Update: Pipeline construction is complete, with a total of 4,600-feet of natural gas pipeline installed between Chapman Highway and Tipton Station Road. Work continues on the new South Knox Gate Station located at 409 Tipton Station Road. The gate station is approximately 45-percent complete as of early October.

Construction continues to progress on the new KUB South Knox Natural Gas Gate Station located at 409 Tipton Station Road.