October 19, 2018 UPDATE –
Pipeline:
Restoration work remains in one area between W. Marine Road and Henry Haynes.
All other restoration work has been completed.
Gate
Station: KUB contractor
Cenergy installed one control building onsite this week. Testing activities
slated for this past weekend have been rescheduled for this coming Sunday and
Wednesday evenings. This work will be isolated to the gate station construction
site with no impacts to customers. Installation of conduit and excavation for
station inlet and outlet piping will continue next week.