Friday, October 19, 2018

South Knox Natural Gas Project


October 19, 2018 UPDATE – 
Pipeline: Restoration work remains in one area between W. Marine Road and Henry Haynes. All other restoration work has been completed.

Gate Station: KUB contractor Cenergy installed one control building onsite this week. Testing activities slated for this past weekend have been rescheduled for this coming Sunday and Wednesday evenings. This work will be isolated to the gate station construction site with no impacts to customers. Installation of conduit and excavation for station inlet and outlet piping will continue next week.