Project Update: Zone 1 –
Complete as of April 2018 with 7,200-feet of main replaced and 64 services;
Zone 2 – Complete as of September 2018 with 9,100-feet of main replaced and 70
services; Zone 3 – Complete as of July 2018 with 11,100-feet of main replaced
and 110 services; Zone 4 – 90 percent complete as of early October with
9,100-feet of main replaced and 60 of 103 services completed (work remains on
Dorchester Drive and Newcastle Drive).