Jackson Avenue Ramps Utility Relocation Project


October 26, 2018 UPDATE – 
Contractor Southern Constructors and their subcontractors completed testing and tie-ins on the domestic and fire protection water lines. Water line connections on a hydrant at Jackson Terminal and an 8-inch line going to Fire Alley are scheduled for Monday, October 29. Final natural gas connections have been moved to next week, October 29-31, due to inclement weather. Wastewater work requiring traffic closures on W. Jackson Avenue is expected to begin in early November. Information on the scope and duration of traffic closures will be communicated in advance, as details are finalized.