December 7, 2018 UPDATE – The block of Patton Street
between Willow Avenue and E. Summit Hill Drive will reopen to normal traffic
flow by midday Friday, December 7, in preparation for the evening WIVK
Christmas Parade in the downtown area. Garney Construction finished pressure
testing the new 36-inch in water main this past week. Additional pipeline
testing and cleaning will take place next week before final tie-ins are made.
The above-mentioned section of Patton Street will close again Monday morning,
December 10, and will remain closed through Friday, December 21, for testing
and cleaning. Additionally, Blackstock Avenue will be reduced to one
alternating lane of traffic near the Heins Street intersection in association
with final pipeline prep work the week of December 10. The final tie-in to
connect the 36-inch main is scheduled to take place the week of December 17.
This work will require a lane closure on E. Summit Hill Drive, and information
will be communicated as details for this last stage of the project are
finalized.
(Downtown Area) Blackstock
Avenue Lane Closure [December 10–14] – KUB contract crews will
close a short section of the westbound lane of Blackstock Avenue between Heins
Street and Hannah Avenue from 7 a.m., Monday, December 10, through 6 p.m.,
Friday, December 14, as work is performed on the water distribution system in
the area. The eastbound lane will remain open and will be used to alternate
traffic through the work zone. Access to area business will be maintained.
Appropriate signage and flaggers will be on site to assist with traffic
control. Follow-up advisories will be issued as necessary.