December 7, 2018 UPDATE  Pipeline: As of November 9, all right-of-way restoration was finished in the areas where the new natural gas pipeline was installed. Gate Station: KUB and crews from contractor Cenergy worked this past week to install fencing and landscaping around the perimeter of the station. Work also continued on installing stone for final pad surfacing, painting all above-ground piping, and final mechanical installations. Painting, remaining installations, and clean-up and restoration activities will continue through next week. Crews will be working to restore the materials storage area, located across from the gate station on Tipton Station Road. Motorists are advised to proceed with caution in this  area due to the ongoing presence of trucks and equipment in association with this work.