Neyland Drive Water Main Project

December 21, 2018 UPDATE – KUB Underground Construction crews implemented lane closures on Neyland Drive, and closed the section of Neyland Greenway between Third Creek and Lake Loudoun Boulevard, on Monday, December 16, as work began to replace the water main in this area. As of the Thursday, December 20, water main installation was completed. Crews will fill and test the line over the weekend prior to returning to work on Wednesday, December 26, to begin connecting service lines to the new main. Additional Neyland Drive lane closures will be needed daily from 7:30 a.m. – 5 p.m. in association with the service line work. KUB crews will not work on the following dates over the holidays: December 24 & 25, 2018, and January 1, 2019.