Neyland Drive Water Main Project
December
21, 2018 UPDATE – KUB
Underground Construction crews implemented lane closures on Neyland Drive, and
closed the section of Neyland Greenway between Third Creek and Lake Loudoun
Boulevard, on Monday, December 16, as work began to replace the water main in
this area. As of the Thursday, December 20, water main installation was
completed. Crews will fill and test the line over the weekend prior to
returning to work on Wednesday, December 26, to begin connecting service lines
to the new main. Additional Neyland Drive lane closures will be needed daily
from 7:30 a.m. – 5 p.m. in association with the service line work. KUB crews
will not work on the following dates over the holidays: December 24 & 25,
2018, and January 1, 2019.