December 14, 2018 UPDATE – Hurst Excavating and its
subcontractors will continue wastewater system rehabilitation work on Towanda
Trail, just south of the Kingston Pike intersection, through Friday, December
21. This section of Towanda Trail will remain closed continuously due to deep
excavation in the area. Access to area residences will be maintained. Paving
and restoration work will continue through next week on a short section of
Mellen Avenue and Dogwood Lane, as weather conditions allow. Construction
activity will continue in off-road easement areas near Sylvan Lane, Hiawatha
Drive, Kingston Park Drive, and on property on the west side of Scenic Drive
near the Kingston Pike intersection. Trenchless rehabilitation methods,
including lining existing pipe, will be used in these off-road areas with no
impacts to traffic. Paving and restoration was completed this past week on
Hiawatha Drive, near the Noelton Drive intersection.
(Sequoyah Hills) Sequoyah Hills
Area Road Closures [December 17-21] – KUB contract crews will implement the below road closures as
needed daily, Monday-Friday,
from 7 a.m. – 5 p.m., December 17 – 21, as work continues
on the wastewater collection system in the area:
· Dogwood Lane between Arrowhead Trail and Noelton Drive
· Arrowhead Trail between Dogwood Lane and Blows Ferry Road
· Mellen Avenue between Lyons View Pike and Arrowhead Trail
Additionally, Towanda Trail between Kingston
Pike and Shawnee Lane will be closed continuously Monday, December 17, through
Friday, December 21, due to extensive excavation. Access to area homes will be
maintained, and flaggers and signs will be on site to assist with traffic
control. Unless otherwise indicated, roadways will be re-opened outside of work hours. Follow-up
advisories will be issued as necessary.