December 14, 2018 UPDATE – The block of Patton Street
between Willow Avenue and E. Summit Hill Drive will remain closed through
Friday, December 21. This section of Patton Street will reopen to normal
traffic flow from December 22-25. The contractor will re-implement the road
closure on Patton Street, and a single lane closure on westtbound E. Summit
Hill Drive, from December 26-28 to complete the final tie-in of the new 36-inch
main to the existing main and to finish paving/restoration work. One westbound
and both eastbound lanes will remain open on this section of E. Summit Hill
Drive. Garney will also reduce the section of Patton Street between E. Jackson
Avenue and Willow Avenue to one alternating lane of traffic on Thursday,
December 20 to set up pumping equipment associated with the water line work.