Friday, December 21, 2018
Depot Avenue Area Water Main Project
December 21, 2018 UPDATE – Following
pressure-testing procedures this week, additional work on the 36-inch water
transmission line is needed in the vicinity of Williow Avenue, east of the
Patton Street intersection. This work will be limited to the shoulder area on
the south side of Willow Avenue with no impacts to traffic through the week of
January 7. The block of Patton Street between Willow Avenue and E. Summit Hill
Drive will be open to normal traffic flow from December 22-25. The Patton
Street road closure will be implemented again starting at 7 a.m. on Wednesday,
December 26. Additional
road and lane closures will be needed for the final tie-in of the 36-inch
transmission main to the existing main near the intersection of Patton Street
and E. Summit Hill Drive. Information on the scope and duration of that work
and traffic impacts will be communicated as details are finalized after the
first of the year. KUB’s contractor will not work on
the following dates over the holidays: December 24 & 25, 2018, and January
1, 2019. Due to holiday schedules, the next blog update will be posted
on January 4, 2019.