December 14, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed. Gate
Station: KUB and crews
from contractor Cenergy finished electrical and mechanical installations on the
station this week. Painting work is scheduled to be completed by the end of
next week. KUB crews will maintain a presence onsite over the next several
weeks leading up to facility commissioning activities in early January 2019.