Friday, October 25, 2019

Holston Hills Natural Gas Project


HOLSTON HILLS NATURAL GAS SYSTEM IMPROVEMENTS  

October 25, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main on Green Valley Drive from S. Chilhowee Drive to Shady Dell Trail
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 5317 Shady Dell Trail up to Green Valley Drive
  • Customer service line connections to the new natural gas main in the following areas:
    • 5505-5500 Crestwood Drive
    • 5405-5512 Holston Hills Road
    • 1502 Cliffside Lane

No comments: