October 25, 2019 UPDATE –
Weekly Update (see attached
maps for corresponding work zones):
Sequoyah Hills Wastewater
Rehabilitation – Construction crews will
work in the following areas next week with intermittent road closures
between 7 a.m. – 5 p.m.:
- Bluff View Road between Southgate Road and Holloway Drive
Crews will also work in
the following off-road easements with minimal traffic impacts:
- Sequoyah Apartments between Kenesaw Avenue and Keowee Avenue
Yard/Easement Restoration –
Hot and dry weather extending into early October has had a major impact on re-seeding
grass and yard/easement restoration efforts. With a return to a more normal
weather pattern, Morgan Construction and its subcontractors have resumed
general clean-up and re-planting grass and placing straw. Restoration may
take several weeks, but work will continue until all construction areas are
repaired.
Closed-circuit Television
Inspection – Crews will continue to
work throughout the Phase 2 area next week. Temporary lane closures will be
implemented as needed when crews are present.
Manhole Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah Park – Morgan Construction and their subcontractors continue to
rehabilitate the existing wastewater main and manholes in Sequoyah Park. See
the attached map showing current work corridors within the park. The park, all
entrances and parking areas, and boat ramp remain open during this work. Morgan
Construction is also maintaining a fenced area in the middle parking lot for
equipment and materials storage. KUB has coordinated work in the park with City
of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills
Association. Informational banners have been placed in the park
entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.