Old Kingston Pike Water Main Project

October 18, 2019 – KUB Underground Construction began installing the new water main on Old Kingston Pike this past Sunday, October 13.  Work started at 4534 Old Kingston Pike and has progressed westward to the intersection of S. Forest Park Boulevard. Water main installation will continue westward on  Old Kingston Pike to the Staub Street intersection next week. Lane and road closures will continue in the immediate work areas with detour routes providing full access to all commercial and residential properties in the area. Detours and alternate routes will be provided to maintain access to all business in the construction zone. Water main replacement is scheduled to last through early January 2020 in this area. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in early January. Final paving and restoration will take place at the conclusion of the wastewater project.