October 18, 2019 Update – Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main on Green Valley Drive from S. Chilhowee Drive to Shady Dell Trail
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 5317 Shady Dell Trail up to Green Valley Drive
  • Customer service line connections to the new natural gas main in the following areas:
    • 5505-5500 Crestwood Drive
    • 5405-5512 Holston Hills Road
    • 1502 Cliffside Lane