August 10, 2018 UPDATE – ZONE 2: KUB contractor Classic City Mechanical worked
service reconnections in the 8200 block of Chesterfield Drive, as well as in
the 8200 block of Bennington Drive. Next week, they will move to the 8300 block
of Bennington Drive, 8200 block of Chesterfield Drive, Westminster Road and the
8200 block of Corteland Drive. ZONE 4: KUB Underground Construction
crews, alongside East Tennessee Pipeline crews, worked on service reconnections
in the 7400 block of Bennington Drive and the 700 block of Shadycrest Drive.
Next week, they will be at the intersection of Vanosdale Road & Bennington
Drive, 7200 block of Vanosdale Road and on Shadycrest Lane.
Friday, August 10, 2018
Depot Avenue Water Main Project
August 10, 2018 UPDATE – Crews were able to reopen
the closed lanes of E. Summit Hill Drive this week, which will remain open
until the new 36-inch main is installed and tested. These crews will maintain a
closure of Patton Street between Willow Street and W. Summit Hill Drive as they
continue work in this area. Additional Garney Construction crews have continued
service tie-ins on the newly installed 8-inch water line on W. Depot Avenue
between Williams Street and N. Central Street and will continue service tie-in
work on W. Depot Avenue between N. Central and Morgan Street next week.
Friday, August 3, 2018
Sequoyah Hills Wastewater Project
August 3, 2018 UPDATE – OVERALL PROJECT UPDATE: Phase 1 construction is approximately 50 percent complete as of
early August. This portion of the project remains on schedule for completion by
January 2019. Sewer pipeline and manhole rehabilitation
has been completed on Scenic Drive and Southgate Road, ahead of the City of Knoxville’s
plans to pave those areas in 2019. Scenic and Southgate have already been paved
by the City. The contractor, Hurst Construction, is performing clean-up
and restoration following deep excavation on Wilani Road. Construction on
Arrowhead Trail is nearing completion, to be followed by clean-up and
restoration. Extensive construction remains for Phase
1 work on Alta Vista Way, Noelton Drive, and Hiawatha Drive through this fall.
Phase 2, which includes rehabilitation of seven miles of wastewater lines, is
scheduled to begin in January 2019. Information regarding Phase 2 will be
communicated this fall as details are finalized.
Weekly Update: Hurst Excavating and its
subcontractors will continue clean-up and restoration work on Wilani Road
between Taliluna Avenue and Southgate Road through next Friday, August 10.
Construction will continue on Hiawatha Drive (between Noelton Drive and Towanda
Trail), and pipe-lining and restoration crews will work in the vicinity of
Arrowhead Trail through next week. Construction requiring road closures will
begin next week on Chippewa Circle and Chickasaw Road. Work on Chippewa Circle
will be divided into two sections to maintain access to detour via Shawnee
Lane.
SPECIAL NOTE – SATURDAY WORK: Crews plan to work between the hours of
7 a.m. and 5 p.m. on Saturday, August 4, to install customer service laterals on the 500 block of Arrowhead Trial. Construction may extend beyond 5
p.m., depending on construction progress and conditions encountered during
excavation. This section of Arrowhead Trail will remain closed through traffic
during construction. Access to driveways will be maintained. Appropriate
traffic control measures will be in place to direct traffic flow around the
work zone.
NOTES: COK Stormwater Work – As indicated on this week’s map, the
City of Knoxville is currently working on the stormwater system on Noelton
Drive near the intersection with Alta Vista Way. This is not part of KUB’s work
in the area. Please contact the City of Knoxville at 311 for more information
about their work in this area. Yard Restoration -- KUB and Hurst
Excavating have noticed that grass recently planted as part of yard restoration
has started to turn brown due to hot, dry weather. Those areas will be
readdressed by the contractor as temperatures decrease during the fall growing
season.
(Sequoyah Hills) Sequoyah
Hills Area Road Closures [August 6-10] – KUB contract crews will implement the below
road closures as needed daily,
Monday-Friday, from 7 a.m. – 5 p.m., August 6-10, as
work continues on the wastewater collection system in the area:
- Chippewa Circle at Noelton Drive
- Wilani Road between Southgate Road and Taliluna Avenue
- Alta Vista Way between Blows Ferry Road and Arrowhead Trail
Additionally, Chickasaw
Road between Cherokee Boulevard and Navaho Road will be closed continuously
from 7 a.m., August 6, through 5 p.m., August 10, due to excavation. Access to
area homes will be maintained, and flaggers and signs will be on site to assist
with traffic control. With the exception of Chickasaw Road, all other roadways
in the area will be re-opened outside of work hours. Follow-up advisories will
be issued as necessary.
South Knox Natural Gas Project
August 3, 2018 UPDATE – OVERALL PROJECT UPDATE: Contractor Cleary
Construction has completed approximately 90 percent of the natural gas pipeline
installation for the project. Approximately 4,600 feet of natural gas main has
been installed and tested as of early August. Grading and site preparation work
for the new South Knox Gate Station at 304 Tipton Station Road is approximately
80 percent complete. The gate station is expected for completion by November
2018.
Weekly Update: Cleary Construction crews
will continue work to put the newly-installed pipeline into service, including
placement of enclosures around the new main line valves. No road closures are
scheduled for next week; however, the closure of the righthand turn lane on
Chapman Highway (between the IHOP/CVS entrance and Mountain Grove Road) has
been extended through August 10, as listed on the map. Gate Station:
Blount Excavating crews continued grading work in preparation for installation
of the structural and equipment foundations next week. Periodic temporary lane
closures may be needed in this area of Tipton Station Road as construction
equipment and vehicles enter and exit the work zones.
(South Knoxville) Chapman
Highway Continuous Lane Closure [Extended, August 3-10] – KUB contract crews will maintain a closure of a short section of
the southbound right turn lane of Chapman Highway beginning at IHOP/CVS to
Mountain Grove Drive, from
5 p.m., Friday, August 3, through 5 p.m., Friday, August 10, as work is performed on the natural gas distribution system
in the in the area. Both southbound lanes, the center turn lane, and
both northbound lanes will remain open during this
time and turn access to Mountain Grove Drive will be maintained. Access to local business will be maintained, and flaggers
and signs will be on site to assist with traffic control.
Depot Avenue Water Line Project
August 3, 2018 UPDATE – OVERALL PROJECT UPDATE: The overall
project is approximately 75 percent complete as of early August. Over 5,100
feet of 36-inch ductile iron pipe have been installed on Blackstock Avenue, Van
Street, W. Fifth Avenue, and Williams Street for the new water transmission
main. An additional 1,890 feet of ductile iron pipe between 8- and 16-inch
diameter have been installed on W. Fifth Avenue, Williams Street, and W. Depot
Avenue. A total of 18 service lines have been reconnected. Remaining work includes the following streets:
- W. Depot between Williams Street and Morgan Street (includes the N. Central Street intersection)
- Morgan Street between W. Depot Avenue and Jackson Avenue
- Jackson Avenue between Morgan Street and Patton Street
- Patton Street between Jackson Avenue and E. Summit Hill Drive
Weekly Update: Garney Construction crews
finished testing the newly-installed 8-inch water line on W. Depot Avenue
between Williams Street and N. Central Street this week. Crews will continue
work on this section of W. Depot Avenue with tie-ins and the start of
installation on the 36-inch main next week. A second crew also began
installation of an 8-inch main on E. Depot Avenue, between N. Central Street
and Morgan Street this week. Paving and restoration work will take place
following installation of the 8- and 36-inch water lines. Crews are expected to
close the Depot Avenue at N. Central Street intersection by mid-August.
Additional information regarding the scope and duration of work in that area
will be communicated as plans are finalized. The closure of both westbound
lanes of E. Summit Hill Drive at Patton Street has been extended through 5 p.m.,
Friday, August 10. Westbound traffic will be detoured to Hill Avenue, Howard
Baker Jr. Boulevard, and Hall of Fame Drive, and other alternate routes include
Martin Luther King, Jr., Avenue, McCalla Avenue, E. Jackson Avenue, and N.
Central Street.
(Downtown Knoxville) East
Summit Hill Drive Lane Closure [Extended, August 3-10] – KUB contract crews will maintain a closure of both westbound
lanes of E. Summit Hill drive at Patton Street from 5 p.m., Friday, August 3,
through 5 p.m.,
Friday, August 10, as work is performed on the water distribution system in the
area. Westbound traffic will be detoured to Hill Avenue, Howard Baker Jr.
Boulevard, and Hall of Fame Drive, and other alternate routes include Martin
Luther King, Jr. Avenue, McCalla Avenue, E. Jackson Avenue, and N. Central
Street. Access to local businesses will be maintained, and flaggers and signs
will be on site to assist with traffic control. Electronic message boards also
will be posted near the Summit Hill Drive/State Street intersection and on
Dandridge Avenue to alert motorists of the traffic pattern change.
West Hills Natural Gas Project
August 3, 2018 UPDATE – OVERALL PROJECT UPDATE: Zone 1 – All work completed
in mid-April, including 7,200 feet of new main and 64 service connections. Zone
2 – Scheduled for completion by October 2018, including 9,100 total feet of
natural gas main. Twenty-three of 70 total service lines have been connected as
of early August. Work remains on Chesterfield Drive, Corteland Drive, and N.
Winston Road in this area. Completion of work in Zone 2 is scheduled for
October 2018. Zone 3 – Construction to install 11,000 feet of natural
gas pipeline and connect 115 services was finished in late July, ahead of
schedule. Zone 4 – KUB Underground Construction crews have installed
approximately 70 percent of the natural gas main in this area, including 10 of
103 service connections. The scope of work in this area was expanded to include
Buckingham Drive, Dorchester Drive, and Newcastle Road. Completion in this area
is scheduled for December 2018. ZONE 2: KUB contractor Classic City Mechanical worked
in the Corteland Drive area this week to connect sections of newly-installed
natural gas main. They will work at 409 N. Winston Road (near West Hills
Baptist Church) and the 8200-block of Chesterfield Drive next week. ZONE
4: East Tennessee Pipeline crews worked on Downing Drive, Rockingham
Drive, Bennington Drive, and Shadycrest Lane this past week. Crews will resume
work on Shadycrest Lane and Rockingham Drive next week. Construction is
also expected to start next week on an additional
3,000 feet of steel main replacement on Dorchester Drive and Newcastle Road
(see attached map). Customers in this area were notified about the start of
construction by mail this week.
Friday, July 27, 2018
Sequoyah Hills Wastewater Project
July
27, 2018 UPDATE – Hurst
Excavating continued open-cut trench work along Wilani Road this past week. Due
to the depth of excavation in this area, Wilani Road will remain closed
continuously to through traffic between Taliluna Avenue and Southgate Road
through August 3. Access will be maintained to driveways on Wilani Road.
Pipe-bursting crews will continue work along Arrowhead Trail, up to Lyons View
Pike, through August 1, with restoration beginning the following day.
Additional crews will be on Alta Vista, between Blows Ferry and Arrowhead
Trail. Hiawatha drive will
also be closed Wednesday, August 1 through Friday, August 10, between Noelton
Drive and Towanda Trail. NOTES: KUB and Hurst Excavating have noticed that grass recently
planted as part of yard restoration has started to turn brown due to hot, dry
weather. Those areas will be readdressed by the contractor as temperatures
decrease during the fall growing season.