Friday, July 27, 2018
Sequoyah Hills Wastewater Project
July
27, 2018 UPDATE – Hurst
Excavating continued open-cut trench work along Wilani Road this past week. Due
to the depth of excavation in this area, Wilani Road will remain closed
continuously to through traffic between Taliluna Avenue and Southgate Road
through August 3. Access will be maintained to driveways on Wilani Road.
Pipe-bursting crews will continue work along Arrowhead Trail, up to Lyons View
Pike, through August 1, with restoration beginning the following day.
Additional crews will be on Alta Vista, between Blows Ferry and Arrowhead
Trail. Hiawatha drive will
also be closed Wednesday, August 1 through Friday, August 10, between Noelton
Drive and Towanda Trail. NOTES: KUB and Hurst Excavating have noticed that grass recently
planted as part of yard restoration has started to turn brown due to hot, dry
weather. Those areas will be readdressed by the contractor as temperatures
decrease during the fall growing season.