December 14, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed. Gate
Station: KUB and crews
from contractor Cenergy finished electrical and mechanical installations on the
station this week. Painting work is scheduled to be completed by the end of
next week. KUB crews will maintain a presence onsite over the next several
weeks leading up to facility commissioning activities in early January 2019.
Friday, December 14, 2018
Monday, December 10, 2018
Neyland Drive Area Utility Upgrade Project
KUB MEDIA ADVISORY
Utility Construction to Close
Section of Neyland Greenway
December 16 Through Mid-January 2019
KUB and its
contractor will close the section of the Neyland Greenway between Third Creek
and Lake Loudoun Boulevard starting Sunday, December 16, and lasting
continuously through mid-January 2019 (weather permitting), to facilitate safe
conditions as work is performed on the water distribution system in this area.
A detour
route around the closed section of the Neyland Greenway is set up on the
University of Tennessee campus via Lake Loudoun Boulevard, Volunteer Boulevard,
Andy Holt Avenue, Joe Johnson Drive, Solutions Way, and the Third Creek
Greenway (see attached map).
To familiarize greenway users with the upcoming changes, signage will be placed at key locations along the detour route, and on the Third Creek and Neyland Greenways, the week of December 10. The impacted section of greenway will be closed continuously throughout the duration of the work. KUB asks park patrons to please respect the signage and barricades in place, and to avoid this section of greenway due to ongoing excavation, as well as the presence of construction equipment, materials, vehicles, and workers.
KUB thanks City of Knoxville Parks and Recreation for their assistance with this project, and its customers for their cooperation. Customers with questions or concerns can call 558-2331 after normal business hours to leave a message that will be followed-up with a call from a KUB representative by the end of the next business day.
To familiarize greenway users with the upcoming changes, signage will be placed at key locations along the detour route, and on the Third Creek and Neyland Greenways, the week of December 10. The impacted section of greenway will be closed continuously throughout the duration of the work. KUB asks park patrons to please respect the signage and barricades in place, and to avoid this section of greenway due to ongoing excavation, as well as the presence of construction equipment, materials, vehicles, and workers.
KUB thanks City of Knoxville Parks and Recreation for their assistance with this project, and its customers for their cooperation. Customers with questions or concerns can call 558-2331 after normal business hours to leave a message that will be followed-up with a call from a KUB representative by the end of the next business day.
Friday, December 7, 2018
South Knox Natural Gas Project Update
December 7, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed. Gate
Station: KUB and crews
from contractor Cenergy worked this past week to install fencing and
landscaping around the perimeter of the station. Work also continued on
installing stone for final pad surfacing, painting all above-ground piping, and
final mechanical installations. Painting, remaining installations, and clean-up
and restoration activities will continue through next week. Crews will be
working to restore the materials storage area, located across from the gate
station on Tipton Station Road. Motorists are advised to proceed with caution
in this area due to the ongoing presence of trucks and equipment in association
with this work.
South Knox
Natural Gas Gate Station construction progress as of early December 2018.
Sequoyah Hills Wastewater Project
December 7, 2018
UPDATE – Hurst Excavating and its
subcontractors completed wastewater system rehabilitation work on Dogwood Lane,
Mellen Avenue, and Hiawatha Drive this past week. Intermittent lane and road
closures will remain in these areas through next week for paving and
restoration. Construction crews will move to Towanda Trail and off-road
easement area near Shawnee Lane next week. The section of Towanda Trail south
of Kingston Pike will be closed continuously to through traffic starting next
Monday, December 10, and lasting through Friday, December 21, due to deep
excavation required in this area. Access to driveways will be maintained.
Paving and restoration work has been completed and the roadways reopened to
normal traffic flow on the lower section of Noelton Drive and on Chippewa
Circle.
Local media coverage: WBIR-TV reporter Shannon
Smith interviewed Stephanie Midgett with KUB Communications this week regarding
ongoing wastewater rehabilitation work in the Sequoyah Hills area and the
Century II utility infrastructure maintenance and replacement program. Click here to view the segment.
(Sequoyah
Hills) Sequoyah Hills Area Road Closures [December 10 – 14] – KUB contract crews will implement the below road closures as
needed daily, Monday-Friday, from 7 a.m. – 5
p.m., December 10 – 14, as work continues on the
wastewater collection system in the area:
- Hiawatha
Drive between Noelton Drive and Towanda Trail
- Dogwood
Lane between Arrowhead Trail and Noelton Drive
- Arrowhead
Trail between Dogwood Lane and Blows Ferry Road
- Mellen
Avenue between Lyons view Pike and Arrowhead Trail
Additionally, Towanda Trail
between Kingston Pike and Shawnee Lane will be closed continuously through
Friday, December 14, due to extensive excavation. Access to area homes will be
maintained, and flaggers and signs will be on site to assist with traffic control.
Unless otherwise indicated, roadways will be
re-opened outside of work hours. Follow-up advisories will be issued as
necessary.
Depot Avenue Area Water Main Project
December 7, 2018 UPDATE – The block of Patton Street
between Willow Avenue and E. Summit Hill Drive will reopen to normal traffic
flow by midday Friday, December 7, in preparation for the evening WIVK
Christmas Parade in the downtown area. Garney Construction finished pressure
testing the new 36-inch in water main this past week. Additional pipeline
testing and cleaning will take place next week before final tie-ins are made.
The above-mentioned section of Patton Street will close again Monday morning,
December 10, and will remain closed through Friday, December 21, for testing
and cleaning. Additionally, Blackstock Avenue will be reduced to one
alternating lane of traffic near the Heins Street intersection in association
with final pipeline prep work the week of December 10. The final tie-in to
connect the 36-inch main is scheduled to take place the week of December 17.
This work will require a lane closure on E. Summit Hill Drive, and information
will be communicated as details for this last stage of the project are
finalized.
(Downtown Area) Blackstock
Avenue Lane Closure [December 10–14] – KUB contract crews will
close a short section of the westbound lane of Blackstock Avenue between Heins
Street and Hannah Avenue from 7 a.m., Monday, December 10, through 6 p.m.,
Friday, December 14, as work is performed on the water distribution system in
the area. The eastbound lane will remain open and will be used to alternate
traffic through the work zone. Access to area business will be maintained.
Appropriate signage and flaggers will be on site to assist with traffic
control. Follow-up advisories will be issued as necessary.
Jackson Avenue Ramps Utility Relocation Project
December 7, 2018
UPDATE – Southern Constructors, Inc.,
has completed wastewater system work on W. Jackson Avenue. Paving and
restoration work was scheduled for completion on W. Jackson Avenue as of 3 p.m.
Friday afternoon, December 7, to accommodate the WIVK Christmas Parade. An
additional day of work will be needed next week to complete
paving and surface restoration in the Jackson Avenue parking lot. Information on the scope and traffic impacts associated
with this work will be communicated as details are finalized.
Wednesday, December 5, 2018
Jackson Avenue Ramps Utility Relocation Project
(Old City) W. Jackson Avenue Overnight Lane Closure [December 6-7] – KUB crews will reduce a
short section of W. Jackson Avenue to one alternating lane of traffic at State
Street between S. Gay Street and S. Central Street from 10 p.m., Thursday,
December 6, through 4 a.m., Friday, December 7, as work is performed on the
electric distribution system in the area. The eastbound lane and sidewalk will
be closed while the westbound lane remains open and is used to alternate
traffic through the work zone. Access to area businesses and residential
driveways will be maintained. Flaggers and signs will be on site to assist with
traffic control.