Friday, July 6, 2018

Depot Avenue Water Main Project

July 6, 2018 UPDATE – Garney Construction and subcontractor crews completed installation of the 36-inch water main on the section of W. Fifth Avenue between N. Broadway and Williams Street. This section of W. Fifth Avenue will remain closed next Monday and Tuesday, July 9 and 10, for paving and curb restoration. W. Fifth Avenue is expected to reopen to normal traffic flow on Wednesday, July 11. Alternate routes around the intersection closure include N. Broadway, Emory Place, King Street, S. Central Street, W. Depot Avenue, and Cooper Street. Crews began installation of the 36-inch main along Williams Street between W. Fifth Avenue and progressing south toward W. Magnolia Avenue on Monday, July 2. Work will continue on Williams Street next week. The W. Magnolia Avenue intersection remains open.