Friday, July 6, 2018
Depot Avenue Water Main Project
July
6, 2018 UPDATE –
Garney Construction and subcontractor crews completed installation of the
36-inch water main on the section of W. Fifth Avenue between N. Broadway and
Williams Street. This section of W. Fifth Avenue will remain closed next Monday
and Tuesday, July 9 and 10, for paving and curb restoration. W. Fifth Avenue is
expected to reopen to normal traffic flow on Wednesday, July 11. Alternate
routes around the intersection closure include N. Broadway, Emory Place, King
Street, S. Central Street, W. Depot Avenue, and Cooper Street. Crews began
installation of the 36-inch main along Williams Street between W. Fifth Avenue
and progressing south toward W. Magnolia Avenue on Monday, July 2. Work will
continue on Williams Street next week. The W. Magnolia Avenue intersection
remains open.