West Hills Natural Gas Project

July 13, 2018 UPDATE –  ZONE 2: KUB contractor Classic City Mechanical worked in the 8100 and 8200-blocks of Bennington Drive this week. They will return to the same area next week while also completing tie-ins at the intersection of Bennington Drive and Corteland Drive. ZONE 3: Crews from KUB Underground Construction and East Tennessee Pipeline worked the 500-block of Broome Road again this week. Next week crews will work on Broome Road at Kempton Lane and Westborough Road. ZONE 4: Crews bored in the new natural gas main on Downing Drive and Shadycrest Drive this week, and they will continue work in the same area next week. Buckingham Drive: Crews will begin installation of 450 feet of natural gas main on Buckingham Drive, between Vanosdale Road and Portsmouth Road, next week. Construction is expected to last through early August in this area. Motorists are advised to expect temporary lane closures and possible delays on Buckingham Drive.