WEST
HILLS GAS July 20, 2018 UPDATE
– ZONE 2: KUB contractor Classic City Mechanical worked in
the 8300-block of Bennington Drive this week. They will work in the 8100 and
8200 blocks of Corteland Drive next week. ZONE 3: Crews from KUB
Underground Construction completed all work in Zone 3
as of Friday, July 20. Crews from this area will shift to Zone 4 next week. ZONE 4: East Tennessee Pipeline crews worked in the
200-block of Buckingham Drive this week, and they will work in that area again
next week. KUB crews will work in the Bennington Drive/Vanosdale Road,
Bennington Drive/Bennington Circle, and Vanosdale Road/Shadycrest Lane
intersections next week. Buckingham Drive: Crews started installation
of 450 feet of natural gas main on Buckingham Drive, between Vanosdale Road and
Portsmouth Road, this past week.
Construction is expected to last through early August in this area. Motorists are advised to expect
temporary lane closures and possible delays on Buckingham Drive.