WEST HILLS GAS July 20, 2018 UPDATE –  ZONE 2: KUB contractor Classic City Mechanical worked in the 8300-block of Bennington Drive this week. They will work in the 8100 and 8200 blocks of Corteland Drive next week. ZONE 3: Crews from KUB Underground Construction completed all work in Zone 3 as of Friday, July 20. Crews from this area will shift to Zone 4 next week. ZONE 4: East Tennessee Pipeline crews worked in the 200-block of Buckingham Drive this week, and they will work in that area again next week. KUB crews will work in the Bennington Drive/Vanosdale Road, Bennington Drive/Bennington Circle, and Vanosdale Road/Shadycrest Lane intersections next week. Buckingham Drive: Crews started installation of 450 feet of natural gas main on Buckingham Drive, between Vanosdale Road and Portsmouth Road, this past week. Construction is expected to last through early August in this area. Motorists are advised to expect temporary lane closures and possible delays on Buckingham Drive.