July 27, 2018 UPDATE – ZONE 2: KUB contractor Classic
City Mechanical worked in the 8100-block of Corteland Drive this week. They
will work in the 8200 block of Chesterfield Drive and the 8300-block of
Bennington Drive next week. ZONE 3: Crews from KUB Underground
Construction completed all work in Zone 3 as of Friday, July 20. Crews from
this area will shift to Zone 4 next week. ZONE 4: East Tennessee Pipeline crews
worked in the 200-block of Buckingham Drive this week and the 7400-block of
Bennington Drive, as well as Shadycrest Drive. Next week, they will continue
work in the 7400-block of Bennington Drive as well as on Bennington Circle and
Shadycrest Drive. KUB has
added 3,000 feet of steel main replacement on Dorchester Drive and Newcastle
Road to the scope of work in Zone 4. Construction is scheduled to begin the
week of August 6. Customers in this area will be notified by mail next week,
prior the start of construction activity.