July 13, 2018 UPDATE – Hurst Excavating continued open-cut trench work along Wilani Road this week. Due to the depth of excavation in this area, Wilani Road will remain closed continuously to through traffic between Taliluna Avenue and Southgate Road through July 20. Access will be maintained to driveways on Wilani Road. Subcontractor paving and restoration crews will continue work in the Calumet Drive area next week. Pipe-bursting crews will continue work along Arrowhead Trail, up to Lyons View Pike. Pipe-lining crews will close one eastbound lane of Kingston Pike between Noelton Drive and Towanda Trail from 9 a.m. – 3 p.m., July 18-20. One eastbound lane and both westbound lanes will remain open. Lining crews will also close one lane on Scenic Drive on Monday, July 16, and work in an off-road easement near Kingston Park Drive. NOTES: As indicated on this week’s map, the City of Knoxville is currently working on the stormwater system on Noelton Drive and Hiawatha Drive. This is not part of KUB’s work in the area. Please contact the City of Knoxville at 311 for more information about their work in this area.  

(Sequoyah Hills Area) Kingston Pike Lane Closure [July 18-20] – KUB contract crews will close a short section of the inside, eastbound lane of Kingston Pike between Anteelah Trail and Noelton Drive daily, Monday – Friday, from 9 a.m. – 3 p.m., Wednesday, July 18, through Friday, July 20, as work is performed on the wastewater distribution system in the in the area. The curbside, eastbound lane will remain open during this time, as will both westbound lanes. Appropriate signs and channeling devices will be on site to assist with traffic control.



No comments:

Post a Comment