South Knox Natural Gas Project


July 6, 2018 UPDATE Pipeline Installation: Cleary Construction crews continued installation of the new natural gas main in off-road easements along Chapman Highway. No road closures are scheduled for next week; however, the righthand turn lane on Chapman Highway (between the IHOP/CVS entrance and Mountain Grove Road) will remain closed through August 3, as listed on the map. Next week, crews will work in the off-road easements near Mountain Grove Road and Henry Haynes Road. Restoration work will continue along the off-road easements between Mountain Grove Road and Tipton Station Road. Gate Station: Blount Excavation crews continued site clearing and grading work in preparation for construction of the new natural gas gate station located at 304 Tipton Station Road. Periodic temporary lane closures may be needed in this area of Tipton Station Road as construction equipment and materials are unloaded. NOTE: Crews will work this Saturday, July 7, in off-road easements near Chapman Highway and Tipton Station Road.

No comments:

Post a Comment