(Old City Area) E. Depot Avenue Road Closure
[November 30 – December 7] – KUB crews will close a short section of E. Depot Avenue between
Morgan Street and N. Central Street continuously from 3 p.m., Friday, November
30, through 3 p.m., Friday, December 7, as work is performed on the water
distribution system in the area. Alternate routes include E. Magnolia Avenue,
E. Jackson Avenue, and Willow Avenue. Signs will be on site to assist with
traffic control. Follow-up advisories will be issued as necessary.

Friday, November 30, 2018
Thursday, November 29, 2018
Depot Avenue Area Water Main Project
November 29, 2018 UPDATE – Garney Construction has
completed all pipe installation for the new 36-inch water main. The process of
filling and testing the line started this week. As part of this work, Patton Street
will remain closed between Willow Avenue and E. Summit Hill Drive through
mid-December. Paving restoration work has been completed, and roads have been
reopened to normal traffic flow on the section of Patton Street between
Campbell Avenue and Willow Avenue, and on Willow Avenue east of the Patton
Street intersection. Sidewalk and curb repairs remain in these areas, but that
work will not affect traffic flow. Once testing and flushing of the new water
main is completed, Garney Construction will make the final tie-in to connect
the new 36-inch main to the existing water main at the E. Summit Hill Drive and
Patton Street intersection. This tie-in work will require a lane closure on E.
Summit Hill Drive in December. Information on traffic impacts will be
communicated as details are finalized. Please see the below video for a detailed project overview with Project Manager Tommy Lawhorn from KUB Water Systems Engineering.
Jackson Avenue Ramps Utility Relocation Project
November 29, 2018 UPDATE – Weekly Update: Southern Constructors, Inc., continued rehabilitation of the
wastewater system on W. Jackson Avenue this week. The full road closure of W.
Jackson Avenue (between S. Broadway and Gay Street) will remain in effect
through 2 p.m., Friday, November 30. W. Jackson Avenue will be reopened to
normal traffic flow at that time and throughout the weekend. The contractor
will re-close this section of W. Jackson Avenue to through traffic starting at 6
a.m. Monday, December 3, through 6 p.m., Thursday, December 6, to complete
final testing of the wastewater system and pavement restoration. Access to
businesses and parking lots in the work zone will be maintained. See the
attached map for alternate routes around this section of W. Jackson Avenue.
South Knox Natural Gas Project
November 29, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed. Gate
Station: All mechanical
installations will be complete on the new South Knox Natural Gas Gate Station
by the end of the week. Work continues around the site as the areas around
underground piping and buried conduit are back-filled. Final grading work and
installation of remaining electrical and instrumentation components will
continue over the next several weeks. Additionally, crews will be onsite
installing fencing around the station perimeter and painting inside the
structure.
Construction continues on the new KUB South Knox Natural
Gas Gate Station, located on Tipton Station Road. The new facility is expected
to be ready for operation by January 2019.
Sequoyah Hills Wastewater Project
November 29, 2018 UPDATE – Weekly Update: Construction activity
resumed this week after the Thanksgiving holiday. Construction crews continue
work on the southern end of Noelton Drive, Dogwood Lane, and short sections of
Hiawatha Drive (east of the Noelton Drive intersection) and Mellen Avenue.
Restoration work is also ongoing on Chippewa Circle. These roadways remain
closed daily between 7 a.m. – 5 p.m. Paving and restoration work has been
completed and the roadways reopened to normal traffic flow on the northern
section of Noelton Drive and Chickasaw Road.
Tuesday, November 27, 2018
Jackson Avenue Ramps Utility Relocation Project
TRAFFIC ADVISORY
(Old City) W. Jackson Avenue
Road Closure [November 28-30] – KUB
contract crews will close a section of W. Jackson Avenue between S. Broadway
and S. Gay Street to traffic from 6 a.m., Wednesday, November 28, through 6
p.m., Friday, November 30, as work is performed on the wastewater collection
system in the area. Local traffic access will be maintained via S. Broadway.
Alternate routes include W. Summit Hill Drive, S. Gay Street, Western Avenue,
and S. Broadway. Flaggers and signs will be on site to assist with traffic
control. Access to local businesses will be maintained. Follow-up advisories
will be issued as necessary.
Wednesday, November 21, 2018
Sequoyah Hills Wastewater Project
There will be no blog/map updates posted this week due to
the shortened work week/ Thanksgiving holiday. The next project update will be
posted the week of November 26. Call 865-524-2911 if you have any questions related
to ongoing work in your area.
Depot Avenue Water Main Project
November
21, 2018 UPDATE – Garney Construction crews completed installation
of the 36-inch water main this week. Filling, testing, and flushing work will
begin on the newly-installed water transmission line when crews return from the
Thanksgiving holiday on Monday, November 26. As part of the filling and testing
procedures, crews will be located two locations along the water pipeline route
- at Van Street (between Blackstock Avenue and Callaway Avenue) and at Patton
Street (between Willow Avenue and Summit Hill Drive). This process will take
approximately one and a half weeks to complete. Once testing and flushing has
been successfully completed, crews will begin making final tie-ins in mid-December.
Paving and restoration is scheduled for Patton Street and Willow Avenue,
including the intersection, the week of November 26 (weather permitting). Once
this work is finished, Patton Street (between Campbell Avenue and Willow
Avenue) and Willow Avenue (area east of Patton Street intersection), and the
Patton Street and Willow Avenue intersection will all reopen to normal traffic
flow. The section of Patton Street between Willow Avenue and Summit Hill Drive
will close starting November 26 and lasting through early December for final
tie-ins. A lane closure will also be needed on Summit Hill Drive in
mid-December. Information on that lane closure will be issued as details are
finalized.
Friday, November 16, 2018
Jackson Avenue Ramps Utility Relocation Project
November 16, 2018 UPDATE – Wastewater
system work requiring a full road closure to through traffic on W. Jackson
Avenue (between S. Broadway and Gay Street) is scheduled for the week of November 26. This closure will remain in effect continuously, Monday
through Friday, November 26-30. Access to
businesses and parking lots in the work zone will be maintained. See the
attached map for alternate routes around this section of W. Jackson Avenue. The
contractor will not work over the Thanksgiving Holiday, November 22-23.
Depot Avenue Water Main Project
November 16, 2018 UPDATE – Garney Construction crews continued excavation
for upcoming installation of the 36-inch water main on the section of Willow
Avenue 300-feet east of the Patton Street intersection, as well as within the
off-road easement adjacent to Patton Street, between Willow Avenue and E.
Summit Hill Drive this week. Crews are scheduled to work this weekend removing rock in the off-road easement area adjacent to Patton Street. Weather and conditions
encountered during excavation have hindered progress, and work will continue in
this area over the next several weeks. Patton Street remains closed to through
traffic between Campbell Avenue and Willow Avenue, and Willow Avenue remains
closed east of the Patton Street intersection. The Patton Street intersection
remains open for left-hand turns westbound onto Willow Avenue, and right-hand southbound turns from Willow Avenue onto Patton Street. The contractor will not
work over the Thanksgiving Holiday, November 22-23. Road closures will remain
in effect due to extensive excavation. Appropriate barricades and traffic control
measures will remain in place.
Sequoyah Hills Wastewater Project
November 16, 2018 UPDATE – Work was slow again
somewhat this week due to weather. Hurst Excavating continued rehabilitation of
the wastewater main and manholes on Noelton Drive between Chippewa Circle and
Alta Vista Way. Crews will continue construction on this section of Noelton
Drive, as well as on Dogwood Lane and a short section of Hiawatha Drive west of
Noelton Drive next week. Paving and restoration work requiring intermittent
daily road closures will continue on the section of Noelton Drive between
Kingston Pike and Chippewa Circle, and along Chippewa Circle, through late
November. Chippewa Circle will remain closed to through traffic this weekend.
Restoration work requiring extensive concrete roadway and curb repairs will
also continue with continuous closures (including this weekend) on Chickasaw
Drive through Wednesday, November 21. The
contractor will not work over the Thanksgiving Holiday, November 22-23.
Starting at the end of the day Wednesday, November 21, all roads will reopen to
normal traffic flow until construction activity resumes on Monday, November 26.
(Sequoyah Hills) Sequoyah Hills Area Road Closures [November 19-21] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., November 19 - 21, as work continues on the wastewater collection system in the area:
(Sequoyah Hills) Sequoyah Hills Area Road Closures [November 19-21] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., November 19 - 21, as work continues on the wastewater collection system in the area:
- Hiawatha Drive between Noelton Drive and Towanda Trail
- Noelton Drive between Kingston Pike and Alta Vista Way
- Chippewa Circle between Noelton Drive
- Dogwood Lane between Arrowhead Trail and Noelton Drive
South Knox Natural Gas Project
November 16, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed.
Gate
Station: KUB contractor
Cenergy crews continued working on instrumentation and electrical items this
week, as well as backfilling recently-installed underground piping. Crews
will finish up mechanical installations next week, then begin clean-up and
final grading of the site the week of November 26. Final painting and
fencing installation are scheduled for the week of December 3, with
commissioning activities are scheduled to begin the week of December 10. The
contractor will not work over the Thanksgiving Holiday, November 22-23.
Monday, November 12, 2018
Jackson Avenue Ramps Utility Relocation Project
November 12, 2018 UPDATE – Construction & Road Closure Postponed: Due to inclement weather
forecast for this week, and the Thanksgiving Holiday the following week,
wastewater system construction requiring a full road closure to through traffic
on W. Jackson Avenue (between S. Broadway and Gay Street) originally scheduled
to start today has been postponed until the week of November 26-30. Once
implemented, this closure will remain in effect continuously, Monday through
Friday. Access to businesses and parking lots in the work zone will be
maintained. See the attached map for alternate routes around this section of W.
Jackson Avenue.
Friday, November 9, 2018
Sequoyah Hills Wastewater Project
November 9, 2018 UPDATE – Work was hindered somewhat
this week due to debris and muddy conditions following the storm and high winds
that hit the Knoxville area early Tuesday morning. Hurst Excavating continued
rehabilitation of the wastewater main and manholes on Noelton Drive between
Chippewa Circle and Alta Vista Way again this week. Crews will continue
construction next week on this section of Noelton Drive, as well as on Dogwood
Lane and a short section of Hiawatha Drive west of Noelton Drive. Paving and
restoration work requiring intermittent daily road closures will continue on
the section of Noelton Drive between Kingston Pike and Chippewa Circle, and
along Chippewa Circle, through November 16. Chippewa Circle will remain closed
to through traffic this weekend. Restoration work requiring extensive concrete
roadway and curb repairs will also continue with continuous closures (including
this weekend) on Chickasaw Drive through November 16.
(Sequoyah Hills) Sequoyah Hills Area Road Closures [November 12-16] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., November 12 - 16, as work continues on the wastewater collection system in the area:
Video featuring an interview with KUB project manager Sam Beck.
(Sequoyah Hills) Sequoyah Hills Area Road Closures [November 12-16] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., November 12 - 16, as work continues on the wastewater collection system in the area:
- Hiawatha Drive between Noelton Drive and Towanda Trail
- Noelton Drive between Kingston Pike and Chippewa Circle
- Noelton Drive between Alta Vista Way and Chippewa
Circle
- Chippewa Circle between Noelton Drive
- Dogwood Lane between Arrowhead Trail and Noelton Drive
Chickasaw Road between
Cherokee Boulevard and Navaho Road will be closed continuously Monday, November
12, through Friday, November 16, due to extensive excavation. Access to area
homes will be maintained, and flaggers and signs will be on site to assist with
traffic control. Unless otherwise indicated, roadways will be re-opened outside of
work hours. Follow-up advisories will be issued as necessary.
Jackson Avenue Ramps Utility Relocation Project
November 9, 2018 UPDATE – Natural gas and water line installations are
complete. Wastewater system work requiring a full road closure to through
traffic on W. Jackson Avenue (between S. Broadway and Gay Street) is scheduled
for next week, November 12-16. This closure will remain in effect continuously,
Monday through Friday. Access to businesses and parking lots in the work zone
will be maintained. See the attached map for alternate routes around this
section of W. Jackson Avenue.
(Old City) W. Jackson Avenue Road Closure [November 12-16] – KUB contract crews will close a section of W. Jackson Avenue between S. Broadway and S. Gay Street to traffic from 7 a.m., Monday, November 12, through 5 p.m., Friday, November 16, and work continues on the utilities in the area. Local traffic access will be maintained via S. Broadway. Alternate routes include W. Summit Hill Drive, S. gay Street, Western Avenue, and S. Broadway. Flaggers and signs will be on site to assist with traffic control. Access to local businesses will be maintained. Follow-up advisories will be issued as necessary.
(Old City) W. Jackson Avenue Road Closure [November 12-16] – KUB contract crews will close a section of W. Jackson Avenue between S. Broadway and S. Gay Street to traffic from 7 a.m., Monday, November 12, through 5 p.m., Friday, November 16, and work continues on the utilities in the area. Local traffic access will be maintained via S. Broadway. Alternate routes include W. Summit Hill Drive, S. gay Street, Western Avenue, and S. Broadway. Flaggers and signs will be on site to assist with traffic control. Access to local businesses will be maintained. Follow-up advisories will be issued as necessary.
Depot Avenue Water Main Project
November 9, 2018 UPDATE – Installation of the 8-inch
water main and follow-up paving and restoration work was completed this week in
the N. Gay Street at W. Depot Avenue intersection, and the road has been
reopened to normal traffic flow. No additional utility work is
scheduled for this area. Garney
Construction crews continued installation of the 36-inch water main on the
section of Willow Avenue 300-feet east of the Patton Street intersection, as
well as within the off-road easement adjacent to Patton Street, between Willow
Avenue and E. Summit Hill Drive this week. Pending weather and conditions
encountered during construction, water main installation is expected to be
complete within the next two weeks.
South Knox Natural Gas Project
November 9, 2018 UPDATE – Pipeline:
As of this week, all right-of-way restoration has been completed in the areas
where the new natural gas pipeline was installed.
Gate
Station: KUB contractor
Cenergy continued work to apply a protective coating on piping that will be
installed underground. Crews also continued conduit installation this week.
Next week, crews will continue coating and backfilling newly-installed pipe.
Friday, November 2, 2018
West Hills Natural Gas Project
November 2, 2018 UPDATE – Final Project Update: ZONE
4 – As of
November 2, construction has been completed on Dorchester Drive and New Castle
Drive, which concludes all natural gas pipeline installations in the West Hills
area one month ahead of the scheduled December 2018 completion date.
Right-of-way restoration work will continue in the neighborhood over the next
several weeks. This will be the final blog update for this project. Please call
KUB at 558-2331 if you have questions about restoration activities. The overall
project, which started in August 2017, included the following:
- Zone 1: 7,200 feet of new main and 64 service connections (completed mid-April 2018)
- Zone 2: 9,100 feet of new main and 84 service connections (completed September 2018)
- Zone 3: 11,000 feet of new main and 115 service connections (completed July 2018)
- Zone 4: 9,400 feet of new main and 103 service connections (completed November 2018)
Totals: 36,700 feet of new main and
366 service connections
South Knox Natural Gas Project
November 2, 2018 UPDATE – Pipeline:
Crews completed seeding of the right-of-way between Henry Haynes Road and W.
Marine Road this past week. Re-seeding was also completed sections of the
right-of-way between Tipton Station Road and Henry Haynes Road. Next week,
crews will perform restoration along the
right-of-way on the south side of Henry Haynes Road. Gate
Station: KUB contractor
Cenergy completed hydrostatic testing and applied protective coating on piping
that will be installed underground. Crews also continued conduit installation
this week. Next week, crews will continue coating and backfilling
newly-installed pipe.
Work
continues to progress at the new KUB South Knox natural gas gate station
located at 409 Tipton Station Road.
Sequoyah Hills Wastewater Project
November 2, 2018 UPDATE – Hurst Excavating continued
rehabilitation of the wastewater main and manholes on Noelton Drive between
Chippewa Circle and Alta Vista Way this week. Next week, crews will continue
construction work on this section of Noelton Drive, as well as on Dogwood Lane
and a short section of Hiawatha Drive west of Noelton Drive. Paving and
restoration work requiring intermittent daily road closures will continue on
the section of Noelton Drive between Kingston Pike and Chippewa Circle, and
along Chippewa Circle, through November 9. Restoration work requiring extensive
concrete roadway and curb repairs will also continue with continuous closures
(including weekends) on Chickasaw Drive through November 16.
Depot Avenue Water Main Project Update
November 2, 2018 UPDATE – Garney Construction crews continued
installation of the 36-inch water main in the Willow Avenue and Patton Street
intersection, as well as within the off-road easement adjacent to Patton
Street, between Willow Avenue and E. Summit Hill Drive this week. Work will
continue on the section of Patton Street between Campbell Avenue and Willow
Avenue. The Patton Street at Willow Avenue intersection has been reopened to
allow left turns from Patton Street on to Willow Avenue, and right turns from
Willow Avenue on to Patton Street. A 300-foot section of Willow Avenue east of
the Patton Street intersection will remain closed next week as water main
installation continues. Garney Construction completed all tie-ins for the
8-inch water main along W. Depot Avenue at the N. Gay Street
intersection. This intersection is currently open, but it will be closed
for paving and restoration during the day on Thursday, November 8. The road
will reopen to normal traffic flow with no further utility work in this area by
the end of the day Thursday.
Jackson Avenue Ramps Utility Relocation Project
November 2, 2018 UPDATE – Contractor Southern Constructors and their subcontractors
completed water line connections on a hydrant at Jackson Terminal and an 8-inch
line going to Fire Alley. Additionally, final natural gas connections were
completed. The contractor will be working on asphalt restoration through
next week. Wastewater work requiring traffic closures on W. Jackson
Avenue is expected to begin in early November. Information on the scope and
duration of traffic closures will be communicated in advance, as details are
finalized