Friday, November 9, 2018

Depot Avenue Water Main Project

November 9, 2018 UPDATE – Installation of the 8-inch water main and follow-up paving and restoration work was completed this week in the N. Gay Street at W. Depot Avenue intersection, and the road has been reopened to normal traffic flow. No additional utility work is scheduled for this area. Garney Construction crews continued installation of the 36-inch water main on the section of Willow Avenue 300-feet east of the Patton Street intersection, as well as within the off-road easement adjacent to Patton Street, between Willow Avenue and E. Summit Hill Drive this week. Pending weather and conditions encountered during construction, water main installation is expected to be complete within the next two weeks.