November 9, 2018 UPDATE – Installation of the 8-inch
water main and follow-up paving and restoration work was completed this week in
the N. Gay Street at W. Depot Avenue intersection, and the road has been
reopened to normal traffic flow. No additional utility work is
scheduled for this area. Garney
Construction crews continued installation of the 36-inch water main on the
section of Willow Avenue 300-feet east of the Patton Street intersection, as
well as within the off-road easement adjacent to Patton Street, between Willow
Avenue and E. Summit Hill Drive this week. Pending weather and conditions
encountered during construction, water main installation is expected to be
complete within the next two weeks.