South Knox Natural Gas Project

November 16, 2018 UPDATE  Pipeline: As of November 9, all right-of-way restoration was finished in the areas where the new natural gas pipeline was installed.

Gate Station: KUB contractor Cenergy crews continued working on instrumentation and electrical items this week, as well as backfilling recently-installed underground piping. Crews will finish up mechanical installations next week, then begin clean-up and final grading of the site the week of November 26.  Final painting and fencing installation are scheduled for the week of December 3, with commissioning activities are scheduled to begin the week of December 10. The contractor will not work over the Thanksgiving Holiday, November 22-23.