November 2, 2018 UPDATE – Contractor Southern Constructors and their subcontractors
completed water line connections on a hydrant at Jackson Terminal and an 8-inch
line going to Fire Alley. Additionally, final natural gas connections were
completed. The contractor will be working on asphalt restoration through
next week. Wastewater work requiring traffic closures on W. Jackson
Avenue is expected to begin in early November. Information on the scope and
duration of traffic closures will be communicated in advance, as details are
finalized