November 2, 2018 UPDATE – Garney Construction crews continued
installation of the 36-inch water main in the Willow Avenue and Patton Street
intersection, as well as within the off-road easement adjacent to Patton
Street, between Willow Avenue and E. Summit Hill Drive this week. Work will
continue on the section of Patton Street between Campbell Avenue and Willow
Avenue. The Patton Street at Willow Avenue intersection has been reopened to
allow left turns from Patton Street on to Willow Avenue, and right turns from
Willow Avenue on to Patton Street. A 300-foot section of Willow Avenue east of
the Patton Street intersection will remain closed next week as water main
installation continues. Garney Construction completed all tie-ins for the
8-inch water main along W. Depot Avenue at the N. Gay Street
intersection. This intersection is currently open, but it will be closed
for paving and restoration during the day on Thursday, November 8. The road
will reopen to normal traffic flow with no further utility work in this area by
the end of the day Thursday.