November 16, 2018 UPDATE – Garney Construction crews continued excavation
for upcoming installation of the 36-inch water main on the section of Willow
Avenue 300-feet east of the Patton Street intersection, as well as within the
off-road easement adjacent to Patton Street, between Willow Avenue and E.
Summit Hill Drive this week. Crews are scheduled to work this weekend removing rock in the off-road easement area adjacent to Patton Street. Weather and conditions
encountered during excavation have hindered progress, and work will continue in
this area over the next several weeks. Patton Street remains closed to through
traffic between Campbell Avenue and Willow Avenue, and Willow Avenue remains
closed east of the Patton Street intersection. The Patton Street intersection
remains open for left-hand turns westbound onto Willow Avenue, and right-hand southbound turns from Willow Avenue onto Patton Street. The contractor will not
work over the Thanksgiving Holiday, November 22-23. Road closures will remain
in effect due to extensive excavation. Appropriate barricades and traffic control
measures will remain in place.
No comments:
Post a Comment