November 29, 2018 UPDATE – Garney Construction has
completed all pipe installation for the new 36-inch water main. The process of
filling and testing the line started this week. As part of this work, Patton Street
will remain closed between Willow Avenue and E. Summit Hill Drive through
mid-December. Paving restoration work has been completed, and roads have been
reopened to normal traffic flow on the section of Patton Street between
Campbell Avenue and Willow Avenue, and on Willow Avenue east of the Patton
Street intersection. Sidewalk and curb repairs remain in these areas, but that
work will not affect traffic flow. Once testing and flushing of the new water
main is completed, Garney Construction will make the final tie-in to connect
the new 36-inch main to the existing water main at the E. Summit Hill Drive and
Patton Street intersection. This tie-in work will require a lane closure on E.
Summit Hill Drive in December. Information on traffic impacts will be
communicated as details are finalized. Please see the below video for a detailed project overview with Project Manager Tommy Lawhorn from KUB Water Systems Engineering.