Sequoyah Hills Wastewater Project

November 2, 2018 UPDATE – Hurst Excavating continued rehabilitation of the wastewater main and manholes on Noelton Drive between Chippewa Circle and Alta Vista Way this week. Next week, crews will continue construction work on this section of Noelton Drive, as well as on Dogwood Lane and a short section of Hiawatha Drive west of Noelton Drive. Paving and restoration work requiring intermittent daily road closures will continue on the section of Noelton Drive between Kingston Pike and Chippewa Circle, and along Chippewa Circle, through November 9. Restoration work requiring extensive concrete roadway and curb repairs will also continue with continuous closures (including weekends) on Chickasaw Drive through November 16.