November 2, 2018 UPDATE  Pipeline: Crews completed seeding of the right-of-way between Henry Haynes Road and W. Marine Road this past week. Re-seeding was also completed sections of the right-of-way between Tipton Station Road and Henry Haynes Road. Next week, crews will perform restoration along the right-of-way on the south side of Henry Haynes Road. Gate Station: KUB contractor Cenergy completed hydrostatic testing and applied protective coating on piping that will be installed underground. Crews also continued conduit installation this week. Next week, crews will continue coating and backfilling newly-installed pipe.



Work continues to progress at the new KUB South Knox natural gas gate station located at 409 Tipton Station Road.