November 2, 2018 UPDATE – Pipeline:
Crews completed seeding of the right-of-way between Henry Haynes Road and W.
Marine Road this past week. Re-seeding was also completed sections of the
right-of-way between Tipton Station Road and Henry Haynes Road. Next week,
crews will perform restoration along the
right-of-way on the south side of Henry Haynes Road. Gate
Station: KUB contractor
Cenergy completed hydrostatic testing and applied protective coating on piping
that will be installed underground. Crews also continued conduit installation
this week. Next week, crews will continue coating and backfilling
newly-installed pipe.