Construction continues on the new KUB South Knox Natural
Gas Gate Station, located on Tipton Station Road. The new facility is expected
to be ready for operation by January 2019.
Thursday, November 29, 2018
South Knox Natural Gas Project
November 29, 2018 UPDATE – Pipeline:
As of November 9, all right-of-way restoration was finished in the areas where
the new natural gas pipeline was installed. Gate
Station: All mechanical
installations will be complete on the new South Knox Natural Gas Gate Station
by the end of the week. Work continues around the site as the areas around
underground piping and buried conduit are back-filled. Final grading work and
installation of remaining electrical and instrumentation components will
continue over the next several weeks. Additionally, crews will be onsite
installing fencing around the station perimeter and painting inside the
structure.